projnum_a vnname m2 sumcontr projtitle projaddres team projnum_b projnum_c mps pct multicd cprojion dprojion astat bstat cstat dstat estat fstat inspectr contractor chrcode am is asofmonth
00052-111 Vista Systems C 8265 COSME WTP DETROIT GENERATOR REPLACEMENT 16015 Racetrack Road, Odessa, FL 33566 30 00052-111 00052-111 P 100 0 04/08 - Process Work Order 04/08 - Award Contract  05/08 - Issue NTP  06/08 - Begin Construction RFP sent out.  October - NTP in process for basis of design report.ŤŠJune 2002 - Design continues.ŤŠMay 27, 2003 - Revised scope and workorder and workorder amendment out for approval.ŤŠAugust 21, 2003 - City Council approves Task Order 00-01-TBE with Tampa Bay Engineering, Inc. in the lump sum amount of $12,138 for additional design improvements and upgrades to the generator and generator building for generator no. 2. December 2004 - Project to be bid with roof replacement and S.C.B #6 project. Five (5) sets of plans & specs sent to Gail O. on 5/24/06 per R. Voakes for review of possible reactivation of project.  Project close out.  Received revised Task Order for additional services 11/9/06. 12/06 Workorder Amendment approval. Consultant 200 A D March
02083-111 Black & Veatch Corporation D 497600 OBERLY PUMPING STATION - DESIGN 6198 - 66 S/N 30 02083-111 02083-111 P 100 0 06/08 - Prepare for Advertisement  07/08 - Advertise  08/08 - Open Bids July 2003 - Recevied draft report.  September 2003 - Draft report received.  May 4, 2004 - Final Basis of Design Report (BODR) received.  August 27, 2004 - Revised Task Order distributed.  January 2005 - Issue Notice to Proceed (NTP) for additional serv- ices (design) to Black & Veatch.  July 21, 2005 - Council award to Revere.  3/06 Cosme change to increase the scope of work. Awaiting schedule from consultant.  7/05/06 Received final plans/specs.  7/06 Pre-bid advertisement.  8/06 ON HOLD to bid with generator project.  10/06 thru 11/06 Complete write-up for generator and seek City council approval. Investigating a prepurchase of three (3) generators (WT, Oberly, Cosme) Bid three together. Collecting data on generators to support sole source purchase 10/06 Prepare Generator Direct Purchase Documents. 420 A D March
03064-111 Black & Veatch Corporation D 344700 WASHINGTON TERRACE PS - GENERATOR #1 SWITCHGEAR MCC VFD ADDITION REPLACEMENT 2801 - 66 A/N 30 03064-111 03064-111 P 100 0 06/08 - Prepare for Advertisement  07/08 - Advertise  08/08 - Open Bids July 2003 - Recevied draft report.  September 2003 -  Draft pump curve report received. Met with team to determine quantity of generators.  May 4, 2004 - Final Basis of Design Report (BODR) received.  August 27, 2004 - Revised Task Order distributed. 7/05/06 Received final plans/specs.  7/06 Pre-bid advertisement.  8/06 ON HOLD to bid with generator project. 9/06 thru 11/06 Complete write-up for generator and seek City council approval. Investigating a prepurchase of three (3) generators (WT, Oberly, Cosme) Bid three together. Collecting data on generators to support sole source purchase. 10/06 Prepare Generator Direct Purchase Documents. 420 A D March
04056-111 McKim & Creed Engineers D 103111 COSME WTP HEADER AND SEQUENCE VALVES REPLACEMENT 16015 Racetrack Road, Odessa, FL 33566 30 04056-111 04056-111 P 100 0 03/08 thru 06/08 - Evaluate Re-bidding/Modifying Scope August 27, 2004 - 95% plan set distributed.  McKim & Creed providing additional site visits to monitor actuator open/close times. Will also modify construction sequence to minimize operatioal impact to plant. 10/06 Finalize Design. 420 A D March
04069-111 Greeley and Hansen Engineers D 49000 US 19 - WHITNEY RD TO SR 60 OVERPASS - 48" WTM RELOCATION US19 from Whitney Road to SR60 overpass 18 04069-111 04069-111 P 100 0 Project Close Out in Progress May 2004 - 30% Plans sent to utility check. June 2004 - Letter to adjoining property owners for easement request. July  2004 - Requested additional As-Builts from FDOT thru Lochner. Septembe 2004 - Obtained additional FDOT utility information. Schedule and cost estimate profile sent to Water Resources. November 2004 - Route alignment study from G&H received. December 2004 - G&H proposal to WR for review and approval. February 2005 - Received 15% plans.  March 2005 - Review FDOT 30% plans.  NTP  to G&H for study.  June 3, 2005 - G&H alignment study to Water Resources for review. June 2005 - Work order to Water Resources for easement acquisition.  2/06 Start field survey. Choose best alignment for 36" & 48" WTM relocations. Obtain FDOT letter on US 19 alignment for 48" WTM and meeting with Marine Max.  3/06 Meet with Water Resources to choose and alignment.  4/06 City Council approval, NTP to G&H.  4/06 Meetings with adjoining property owners on 36" WTM.  6/29/06 Meeting scheduled with adjoining property owners on 36" WTM.  6/06 Recommend alignment to WR after receiveing SUE data from FDOT.  JPA Agreements and TSP submittal to FDOT for approval. Marine Max & Harborside have agreed to provide Temporary Construction Easement (TCE) at no cost for 36" relocation. FDOT have agreed to provide and easement at Don Pablos for the 36" relocation.  Marine Max will not provide an easement for 48" relocation. 420 A D March
05046-111 Greeley and Hansen Engineers D 368065 COSME WTP GROUND STORAGE TANK AND VALVE REPLACEMENT 16015 Racetrack Road, Odessa, FL 33566 07 05046-111 05046-111 P 95 0 04/08 - Prepare 100% Design  05/08 - Submit 100% Design  06/08 - Submit for Permits  07/08 - Finalize Bid Documents January 14, 2005 - Kick-off meeting.  April 1, 2005 - Preliminary PDR received.  April 29, 2005 - Preliminary PDR review meeting. September 2, 2005 - Draft PDR review meeting. 10/06 Request Design Proposal from G&H. 420 A D March
06046-110 Marine Contracting Group, Inc. C 78000 ARTERIAL CHANNEL C DREDGING Eckerd College Area 30 06046-110 06046-110 P 1 0 Continue Dredging 1/06 Complete survey and seagrass mapping.  2/06 Permit pre-application meeting.  4/06 Permit application; FDEP, ACOE and PCWNA. 10/06 Finalize Permits. Tony Corson Marine Contracting Group, Inc. 200 A C March
06076-111 Greeley and Hansen Engineers D 122500 COSME HIGH SERVICE PUMP & PLANT INSTRUMENTATION UPGRADE 16015 Racetrack Road, Odessa, FL 33566 30 06076-111 06076-111 P 100 0 Project Close Out in Progress 5/06 Kick-off meeting.  6/06 Data gathering.  8/06 Capacity report. Analysis of pumping capacity expected 7/24/2006.  9/06 Receive analysis of pumping capacity.  10/06 Design continues. Review with Cosme to develop draft design scope.  12/06 Final Buildi ing Study scope development for density. 420 A D March
06100-111 City D 0 US 19 WHITNEY ROAD TO SR 60 OVERPASS - 36" WTM RELOCATION US 19 Whitney Road to SR 60 overpass 18 06100-111 06100-111 P 0 0  Negotiate Easement with FDOT, Meeting with City/FDOT Senior Staff JPA documents sent to FDOT 8/06.  Don Pablos FDOT agreement to provide easement and  Temporary Construction Easement (TCE) to City. 200 M D March
06100-211 Greeley and Hansen Engineers D 87801 US 19 WHITNEY ROAD TO SR 60 OVERPASS-36" WTM RELOCATION AT ALLENS CREEK US 19 Whitney Road to SR 60 at Allens' Creek 18 06100-211 06100-211 P 92 0 04/08 - Submit Permit Applications  05/08 - Prepare 100% Design 420 A D March
06100-311 Greeley and Hansen Engineers D 98684 US 19 WHITNEY ROAD TO SR 60 OVERPASS - 48" WTM RELOCATION - US 19 SOUTH US 19 Whitney Road to SR 60 Overpass - US 19 S 18 06100-311 06100-311 P 50 0 04/08 - Negoitate Agreement with FDOT  05/08 - 90% Design  05/08 - Submit 90% Design to FDOT 420 A D March
06100-411 Greeley and Hansen Engineers D 82389 US 19 WHITNEY ROAD TO SR 60 OVERPASS - 48" WTM RELOCATION - US 19 PHASE 2 NORTH US 19 Whitney Road to SR 60 Overpass - US19 PH2N 18 06100-411 06100-411 P 60 0 04/08 - Negoitate Agreement with FDOT  05/08 - 90% Design  06/08 - Submit 90% Design to FDOT 420 A D March
06102-111 Advanced Engineering & Design, Inc. D 37231 46 A/N FROM 62 S/N TO 80 S/N - ROAD WIDENING PROJECT- WATERMAIN RELOCATIONS 46 A/N from 62 S/N to 80 S/N 18 06102-111 06102-111 P 97 0 03/08 - Submit DEP Permit  03/08 - Submit Final Design to County  04/08 - Receive County Review Comments 10/06 Submit JPA and Advanced proposal to City Council. 420 A D March
06109-111 Advanced Engineering & Design, Inc. D 15501 BRIDGE - JOE'S CREEK & 62 S/N DRAINAGE IMPROVEMENTS - 8" WM REPLACEMENT Joe's Creek & 62 S/N 18 06109-111 06109-111 P 97 0 03/08 - Finalize Current Activities  04/08 - Initiate Project Close Out 9/06 NTP to Advanced Engineering. Project scope increased from 42 A/N to 46 A/N.  Revised JPA sent to Pinellas County. Advanced Engineering to provide an Engineers Estimate by 10/06. 11/06 Plans and engineer's estimate. 420 A D March
07046-121 City D 0 WATER TRANSMISSION MAIN 36" & 48" SURVEY AND AS-BUILT UPDATE 66  Street North 18 07046-121 07046-121 P 15 0 04/08 - Submit 36" Survey to WRD  04/08 - Continue Work on 48" Main  05/08 - Submit 48" Survey to WRD 200 M D March
07082-110 City D 0 CLAM BAYOU LITTER PREVENTION EDUCATION CAMPAIGN Clam Bayou 18 07082-110 07082-110 P 25 0 04/08 - Install Signs 200 M D March
08034-111 Advanced Engineering & Design, Inc. D 6821 PINELLAS BAYWAY BRIDGE FDOT 256903-1-52-02 Pinellas Bayway 18 08034-111 08034-111 P 5 0 04/08 - FDOT Review  04/08 - Revise Plans per FDOT Comments 420 A D March
08038-111 Carollo Engineers, P.C. D 87670 COSME WTP - FACILITIES AND OPERATIONS EVALUATION 16015 Racetrack Road, Odessa, FL 33566 29 08038-111 08038-111 P 100 0 04/08 - Finalize Project  05/08 - Initiate Project Close Out 420 A D March
08042-119 Mactec Engineering & Consulting, Inc. D 4865 EXECUTIVE DRIVE IMPROVEMENTS Executive Drive from 34 S/N to Heron Blvd 07 08042-119 08042-119 P 95 0 05/08 - Finalize Right-of-Way by Economic Development  06/08 - Begin Construction 420 A D March
08046-111 Wetlands by Design C 3300 COSME VEGETATION CONTROL IN POND AND DITCH 16015 Racetrack Road, Odessa, FL 33566 39 08046-111 08046-111 P 100 0 04/08 - Finalize Project  05/08 - Initiate Project Close Out 200 M D March
03089-111 Wharton-Smith Inc. C 4520000 NW WRF - DIFFUSED AERATION CONVERSION 7500 - 26 A/N 07 03089-111 03089-111 P 70 1 4/08 - Continue Construction. 5/08 - Continue Construction. 6/08 - Continue Construction January 2004 - North aeration tank drained and cleaned.  January 23, 2004 - Technical memorandum on new blower building submitted by MPI.  February 3, 2004 - Review meeting to discuss blower building.  March 3, 2004 - Mactec submitted report on inspectio November 4, 2004 - City Council award for final design Task Order.  May 16, 2005 - 75% design review. July 19, 2005 - Refeived 90% plans and specifications. July 25, 2005 - Plans and specifications forwarded for review. July 28, 2005 - Engineer estimate forwarded.  3/06 Preadvertisement meeting, building permit.  4/06 FDEP permit and Building Permit applications.  9/06 Final plans & specs.  10/06 Advertise.  12/06 Open bids. Jim Mallen Wharton-Smith, Inc. 200 A C March
03103-111 Advanced Engineering & Design, Inc. D 144160.4 PINELLAS BAYWAY FORCE MAIN REPLACEMENT-PHASE 2 (DESIGN & BIDDING) Pinellas Bayway 07 03103-111 03103-111 P 100 1 04/15/08 - Open Bids  04/08 - Evaluate Bids  05/08 - Award Contract  06/08 - Begin Construction September 24, 2003 - Issued Notice to Proceed to Advanced Engineering.  December 11, 2003 - Meeting with FDOT on site.  May 7, 2004 - 75% review meeting with Water Resources Department.  August 4, 2004 - 90% review meeting with WRD.  January 19, 2005 - Review meeting to revise design.  March 2005 - Reviewed scope and fee, negotiation and work order amendment pending.  Due to the change of scope of work this project will re-start as work order amendment.  April 22, 2005 - Project status meeting. Workorder Amendment forwarded for approval. June 16, 2005 - City Council contract award. June 29, 2005 - NTP. August 2005 - Survey soft bore.  3/06 Preadvertisement meeting.  4/06 Awaiting clearance from Progress Energy for final design. 5/06 95% Design. 10/06 Obtain FDOT Permit. 420 A D March
03307-017 Ervin Bishop Construction C 81124.75 REBUILD NORTHWEST COMMUNITY CENTER 5801 - 22 A/N 42 03307-017 03307-017 P 1 Closeout project and issue final payment. 03/31/08- Final payment pending repair of roof leaks. 200 A March
04025-002 City X 0 PASADENA AVE (SR 693) FDOT FPID 257076 Pasadena Avenue and 66th Street 18 04025-002 04025-002 P 100 1 04/08 - City to Add Thermo Plastic Striping  05/08 - Submit Final Reimbursement to FDOT May 4, 2004 - Permit application to FDOT.  June 21, 2004 - FDOT utility permit for water main relocation received, permit expires October 17, 2004.  June 17, 2004 - FDOT permit approved, #04-H-799-0047.  September 2004 - FDOT permit extension obtained. February 7, 2005 - Project commenced.  March 2005 - Mast arm conflicts completed. June 2005 - MOT plan to FDOT for 27" sanitary sewer relocation. August 2005 - All Water Resources relocations completed.  2/06 Commence 27" sanitary sewer replacement. 3/06Resurface Pasadena Avenue.  4/06 Obtain reimbursement funds from FDOT.  WR obtaining revised prices from Purcell and All american.  4/06 Commence construction on 27" sanitary sewer.  FDOT evaluating alternatives: 1. Proving additional LAP money. 2. FDOT doing the work under Fast Response Contracts.  Prepare bid documents for Superpavement of Pasadena. FDOT offer to increase LAP funding from $56,000 to $180,000 with "Marshall" asphalt to City specs. Send specs to FDOT for approval. Obtain revised quote from Purcell for day time work.  Project to be re-bid in 2007 Annual Resurfacing Contract. 200 M D March
04063-111 Westra Construction Corporation C 4052000 NW WRF - HEADWORKS IMPROVEMENTS 7500 - 26 A/N 07 04063-111 04063-111 P 99 1 4/08 Project close out. February 24, 2004 - Limited Notice to Proceed (NTP) issued to Parsons Engineering Science (PES). March 16, 2004 - Kick-off meeting.  April 1, 2004 - City Council approved Task Order with PES. May 5, 2004 - Receive draft technical memorandum. May 13, 2004 Issue full Task Order NTP.  May 27, 2004 - Review meeting of Technical memorandum.  September 17, 2004 - Work order for structural investigation complete.  December 10, 2004 - NTP for Grit Removal preliminary design.  April 1, 2005 - Workorder Amendment 2 approved.   May 19, 2005 - City Council award for final design.  June 1, 2005 - Issue Notice to Proceed for final design to Parsons Water and Infrastructure.   June 20, 2005 - Kick-off meeting for final design.   June 21, 2005 - Issue Notice to Parsons  Water and Infrastructure for Survey and Geotechnical. July 15, 2005 - Received 60% design. July 15, 2005 - 60% design submitted for review.  3/06 Advertise for bids.  4/06 Bidding process Open bids.  5/06 Bid evaluation, workorder amendment,City Council Agenda.  7/06 Contract agreement execution.  8/06 NTP for construction, shop drawings. 9/06 Construction commencement. 10/06 Contractor mobilize.  12/06 Excavate and relocate piping and electrical system. Mark Laney Westra Construction Corporation 200 A C March
05032-111 Advanced Engineering & Design, Inc. D 14000 PARK STREET/STARKEY ROAD - TYRONE BLVD TO 84 LANE N PID#864 Park Street/Starkey Road from Tyrone Blvd to 84 18 05032-111 05032-111 P 100 1 04/08 - Consultant to Submit Revised 30% Plans  04/08 - Submit Revised 30% Plans to County  05/08 - Inititate Project Close Out  06/08 - Close Out Project May 12, 2005 - Utility coordination meeting.  May 2005 - SUE information  completed and included in Pre-final plans.  May 2005 - Received pre-final plans from URS phase 2. May 2005 - Phase 2 Tyrone Blvd to 54 delayed until 2008.  1/06 Field review. 2/06 Revise scope after Water Resources meeting.  3/06 Commence 30% design utility review.  Agree preliminary layout with WRD.  Put ON HOLD until 46 Avenue design is complete. 10/06 Preliminary design by Advanced Engineering continues. NTP issued to Advanced Engineering 10/24/06 for 30% plans and a revised engineers estimate. 420 A D March
05103-112 Owen Ayers & Assoc. Inc. X 28518.65 SIDEWALK - PEDESTRIAN BRIDGE - PARK S/N BETWN 5 A/N & COUNTRY CLUB WAY Park Street between 5 A/N and Country Club Way 04 05103-112 05103-112 P 100 1 Completed As-Built drawings and distributed.  Project close out. August 2005 - Survey completed. Plans are at the 50% complete stage. Wooden beams for this structure shall be ordered as soon as possible (ASAP). 50% plans submittal was forwarded to Pinellas County for review and comments. Discussion with SWFWMD for permit underway. They request elevation for bridge be at the one-hundreds year flood level. Submit Right-of-Way permit application to County. Received comment. Met with County. Revised plans and submitted 4 sets for review for pedestrian bridge (timber) and concrete sidewalks.  3/06 Bridge construction and South approach is completed. Awaiting one guy wire to be relocated by cable company and then will construct North approach and begin sidewalk construction.  2/06 Received County R/W permit. Construction on bridge started. Power & Phone Co. are relocating the guide wires for approved sidewalk.  3/06 Bridge construction and South approach is completed. Awaiting one guy wire to be relocated by cable company and then will construct North approach and begin sidewalk construction.  City completed timber pedestrian sidewalk bridge and concrete sidewalk approaches to just before intersection s of 5 Avenue /Park Street and 9 Avenue/Park Street. County completing sidewalks at the above intersections, including ramps.  6/06 County completed concrete sidewalk at Country Club intersection and modified intersection at Park street. After relocating Admiral Farragut signat 5 Avenue and Park Street intersection, County 420 A D March
06066-111 Boyle Engineering Corporation D 230528 LIFT STATION 61 - PASADENA MASTER REHABILITATION 6800 Travelers Way South 07 06066-111 06066-111 P 60 1 04/08 - Prepare 90% Design  05/08 - Prepare 90% Design  06/08 - Review 100% Design 4/06 Data gathering. 10/06 Final report. Submit final report to the contributing entities. 420 A D March
06083-112 Sprinkle Consulting, Inc. D 12320 TRAFFIC CIRCLE - PARK S/S & VILLA GRANDE A/S Park S/S & Villa Grande A/S 33 06083-112 06083-112 P 95 1 04/08 - Finalize Evaluation with Neighborhood Associaton  05/08 - Revise Design As-needed  06/08 - Finalize Bid Documents 4/23/06 Workorder completed.  6/19/06 Kick-off meeting. Survey in progress.  8/06 Survey completed.  10/06 Review Draft Preliminary Design. 420 A D March
06101-110 Marine Contracting Group, Inc. C 83800 ARTERIAL CHANNEL "A" DREDGING 1700 Park Street North 30 06101-110 06101-110 P 1 1 Continue Dredging 7/06 Work order approved awaiting schedule from Survey.  10/06 Finalize Permits. Tony Corson Marine Contracting Group, Inc. 200 A C March
07036-112 City D 0 SIDEWALK - PARK S/N AT ELBOW LANE N Park Street at Elbow Lane North 23 07036-112 07036-112 P 0 1 05/08 - Begin Construction by City Forces 200 M D March
07038-110 PBS & J Incorporated D 74396 JUNGLE LAKE OUTFALL STORM DRAINAGE IMPROVEMENTS Between Jungle Lake and Boca Ciega Bay 01 07038-110 07038-110 P 15 1 04/08 - Begin Detail Design  04/08 - Council Award of Task Order  05/08 - Continue Design 420 A D March
07071-111 APAC Southeast, Inc. C 127605.85 PASADENA AVENUE (SR 686) FDOT-FPID 257076 PASADENA AVENUE (SR 686) 18 07071-111 07071-111 P 100 1 04/08 - City to add Thermoplastic Striping  05/08 - Invoice FDOT 200 A D March
07076-111 City D 0 BEAR CREEK BRIDGE WM @ MANGO A/S - BRIDGE & DRAINAGE IMPROVEMENTS Bear Creek Bridge at Mango A/S 18 07076-111 07076-111 P 5 1 04/08 - Review County Shop Drawings 200 M D March
08045-110 George F. Young, Inc. D 24805 ADMIRAL FARRAGUT DREDGING 501 Park Street North 30 08045-110 08045-110 P 0.6 1 03/08 thru 06/08 - Permit Reviews 420 A D March
08050-120 City D 0 BEAR CREEK STORMWATER INJECTION WELL SYSTEM PLUGGING AND ABANDOMENT Bear Creek 45 08050-120 08050-120 P 5 1 04/08 - Prepare Design  04/08 - Submit FDEP Permit  05/08 - FDEP Review  06/08 - Finalize Bid Documents 200 M D March
08212-117 City D 0 SWIMMING POOL IMPROVEMENTS FY08 - WALTER FULLER 7883 - 26 A/N 43 08212-117 08212-117 P 1 Complete work by mid April, test balance, put pool back in operation. 3/31/08 Contract issued and Progressive Pools to finish by late April. Expect to have the pool back into operation by late April at.  the earliest. 200 M March
08229-017 City D 0 WALTER FULLER MASTER PLAN IMPROVEMENTS 7891 - 26 A/N 42 08229-017 08229-017 P 1 Complete DD drawings.  Develop priority listing and estimate of probable cost.  Schedule public input meeting. 03/31/08 Design started in March 2008. First portion of survey to be completed April 2008. 200 M March
00032-311 City D 0 RECLAIMED WATER SYSTEM - PCCP REPLACEMENT - PHASE II 1 S/N from 72 A/N TO 78 A/N & 1 S/N along 77 A/N 07 00032-311 00032-311 P 35 2 Project on Hold 200 M D March
00064-119 Tampa Bay Engineering, Inc. D 374755.73 GANDY BLVD WIDENING FROM 28 S/N TO DR MARTIN LUTHER KING JR S/N (9 S/N) Gandy Blvd from 28 S/N to Dr Martin Luther King 07 00064-119 00064-119 P 95 2 04/08 - Finalize Land Swap & Construction Agreement  04/08 - NTP for PDE Study  04/17/08 - Council Approve LAP  05/08 - Add Federal Requirements to Specifications  06/08 - Council apporve Land Swap & Construction Agreement January 16, 2003 - Received SWFWMD permit.  January 17, 2003 - Received FDOT permit.  12/05 Follow-up meeting with FDOT regarding upcoming project.  1/06 City/FDOT decision regarding construction phase of this project.  2/27/06 Meeting with FDOT regard- ing land swap for Gandy/16th Street. 9/06 Negotiate  with FDOT regarding land swap.  10/06 City Council approval of the land swap with FDOT. 310 A D March
01062-119 Tampa Bay Engineering, Inc. D 66918 GANDY / 16 S/N SERVICE ROAD REALIGNMENT Gandy Blvd / 16  S/N Service Road 07 01062-119 01062-119 P 95 2 04/08 - Finalize Land Swap & Construction Agreement  04/08 - NTP for PDE Study  04/17/08 - Council Approve LAP  05/08 - Add Federal Requirements to Specifications  06/08 - Council apporve Land Swap & Construction Agreement Received 100% plans & specifications. 310 A D March
02073-110 City D 0 70 A/N AND VICINITY SDI - SMMP N-1-1 70 A/N and Vicinity 01 02073-110 02073-110 P 30 2 Hydraulic Evaluation of Channel September 2003 thru November 2004 - No progress due to other priorities.ŤŠOctober 2004 - Change in design status. September 2003 thru November 2004 - No progress due to other priorities. October 2004 - Change in design status. September 2005-Indications are the proposed project N-1-1 alone cannot succeed in solving the flooding deficiencies. Additional project(s) will be checked to determine scope. Limited budget will likely result in project cancellation. 11/05 No further analysis will be made until mangrove trimming in April 2006.  5/06 Review site and model after mangrove trimming.  5/06 Awaiting confirmation of Mangrove trimming. solving the flooding deficiencies. Additional project(s) will be checked to determine scope. Limited budget will likely result in project cancellation. 11/05 No further analysis will be made until mangrove trimming in April 2006.  5/06 Review site and model after mangrove trimming.  5/06 Awaiting confirmation of Mangrove trimming. Drainage operations requests a letter to Pinellas County seeking permission to trim mangroves.  8/06 Prepare and submit letter in behalf of (Drainage operations requests a l letter to Pinellas County seeking permission to trim  mangroves.) 10/06 Submit County Permit to remove mangroves. 200 M D March
03102-119 Kimmins Contracting Corp. C 1130462.84 28 S/N & 118 A/N INTERSECTION RECONSTRUCTION 28 S/N & 118 A/N 07 03102-119 03102-119 P 99 2 3/08  OTED Site Visit.  4/08  Receive OTED Reimbursement. January 8, 2004 - Meeting with Pinellas County and SWFWMD.  March 1, 2005 - NTP for sidewalk design.  March 24, 2004 - Right-of-way permit application to Pinellas County Public Works Department.  May 28, 2005 - OTTED report submitted for reimbursement. June 24, 2005 - Received 100% plans.  4/06 Bid opening and bid evaluation.  5/06 Low qualified bidder was Kimmins Contracting in the amount of $1,170,455.  6/06 City Council award preparation.  6/15/06 City Council award.  8/06 Shop drawings submitted. 9/06 Shop drawing review process. 10/06 Start construction. Tim Hume Kimmins Contracting Corporation 200 A C March
04037-111 Spectrum Underground, Inc. C 1488869.1 LIFT STATION #42 - NEW 24-INCH FORCE MAIN - JIM WALTERS 10201 - 9 S/N 07 04037-111 04037-111 P 97 2 04/08 - Contractor to Complete Construction  05/08 - Punch List  06/08 - Close out construction Contract May 26, 2004 - Preapplication meeting with FDOT.  October 15, 2004 - FDOT permit received.   October 28, 2004 - FDEP permit received.   January 31,, 2005 - Preadvertisement meeting.  March 30, 2005 - Pre-bid meeting held.  April 19, 2005 - Bids opened. July 7, 2005 - City Council award. July 2005 - Preconstruction meeting, Issue Notice to Proceed. September 20, 2005 - Preconstruction conference. 11/05 Shop drawing review and approval.  3/06 Fourth S/N directional bore completed; Gandy Blvd lane crossin underway. Open cut construction continues.  7/06 Locate and retrieve Gandy Blvd bore.  10/06 Retrieve lost bore. Chuck Perry Spectrum Underground, Inc. 200 A C March
05088-111 TBE GROUP, INC. X 97699 LS 69 ANALYSIS 9399 - 28 Street North 07 05088-111 05088-111 P 1 2 6/07 Project Close Out in Progress May 23, 2005 - Workorder approved. June 7, 2005 - Notice to Proceed issued to TBE for $30,855.00. June 15, 2005 - Meeting with Pinellas County Public Works Department to discuss the scope of work.  June 24, 2005 - Memo review meeting.   June 2005 - Received project Memorandum. September 16, 2005 - Work order amendment approved final design plans and Technical Memo for ultimate flow projections.  4/06 Final report. 10/06 Finalize Report.  12/06 Final report review meeting. 420 A D March
05387-019 City D 0 NORTH BRANCH ROOF WATERPROOFING 861 - 70 A/N 44 05387-019 05387-019 P 2 03/31/08 Project still on hold 200 M March
06120-119 TBE GROUP, INC. D 210705 GATEWAY AREA WIDE DRI BUILD-OUT EXTENSION TRAFFIC STUDY Gateway area 07 06120-119 06120-119 P 90 2 04/08 - Prepare 95% Submittal  05/08 - Review 95% Submittal  06/08 - Finalize DRI 420 A D March
07004-710 City D 0 SIDEWALK - 4 S/N FROM 110 TO 112 A/N 4 S/N FROM 110 TO 112 A/N 23 07004-710 07004-710 P 90 2 Construction by City Forces                                                   Add handrail per FDOT 200 M D March
07043-112 City D 0 TRAFFIC SEPARATOR 94 A/N WEST OF 4 S/N   94 A/N WEST OF 4 S/N 37 07043-112 07043-112 P 95 2 Project Close Out in Progress 200 M D March
07080-110 City D 0 112 A/NE MANGROVE MITIGATION 112th Avenue Northeast 18 07080-110 07080-110 P 2 04/08 - Process Work Order 200 M D March
08031-112 City D 0 ACCELERATION LANE - DR MARTIN LUTHER KING JR STREET/94 A/N Dr Martin Luther King Jr Street / 94 A/N 37 08031-112 08031-112 P 95 2 04/08 - Finalize Design and Construction Cost  05/08 - To SWTOD for Construction  06/08 - Initiate Construction 200 M D March
08219-017 Wannemacher Russell Architects, Inc. D 83936 WILLIS JOHNS CENTER IMPROVEMENTS 6635 Dr MLK Jr S/N 42 08219-017 08219-017 P 2 Develop construction estimates.  Proceed with construction documents provided estimate is within budget. 3/31/08 Reviewed schematic design with recreation staff.  Continue schematic design 410 A March
04042-111 Wharton-Smith Inc. C 2547000 NE WRF GRAVITY BELT THICKENER REPLACEMENT 1160 - 62 A/NE 07 04042-111 04042-111 P 30 3 04/08 - Continue Construction  05/08 - Continue Construction  06/08 - Continue Construction December 4, 2003 - NTP issued to consultant for Basis of Design Report (BODR).  January 8, 2004 - BODR kick-off meeting.  March 3, 2004 - Receive draft BODR.  March 23, 2004 - Draft BODR design review.  April 13, 2004 - Tampa Bay Engineering (TBE) submit ted revised site layout.  April 29, 2004 - Site layout review meeting.  May 19, 2004 - Receive final BODR.  June 7, 2004 - Work order amendment circulated for signatures.  July 16, 2004 - Limited NTP for detail design.  August 3, 2004 - Design kick-off meeting.  February 22, 2005 - 90% plans & Specifications.  March 17, 2005 - 90% design review meeting held.  April 14, 2005 - 100% plans.  May 23, 2005 - Received 100% plans and specifications.  May 23, 2005 - 100% plans and specifications distributed for review.  June 6, 2005 - 100% review meeting.  August 3, 2005 - 100% review meeting. August 30, 2005 - Application for building permit.  2/01/06 Prebid meeting.  2/16/06 Bid opening.  4/06 Bids to high. Combine with NW Diffused Aeration and bid in June 2006. 10/06 Advertise.  12/06 Open bids. Jim Mallen Wharton-Smith, Inc. 200 A C March
04061-110 United Rentals Highway Technologies, Inc D 0 FDOT LAP - SHORE ACRES BICYCLE LANES Shore Acres 33 04061-110 04061-110 P 100 3 05/08 - Request Final LAP Reimbursement  06/08 - Initiate Project Close Out March 18, 2004 - City Council approved FDOT LAP agreement.  April 2004 - Execute LAP.  June 2004 - Design started.  July 30, 2004 - Preadvertisement meeting held.  September 16, 2004 - Contract awarded.  September 2004 - Part of project (62nd A/N)ON HOLD due to change in scope of work.  December 1, 2004 - Preconstruction meeting for Shore Acres bicycle lanes. 62 A/N between Bayou Grand and First Street is still ON HOLD> Awaiting work order amendment approval.  January 2005 - Survey for phase 2 has been completed (62 A/N).  January 5, 2005 - Design for 62 A/N commenced.  April 2005 - Additional survey, design started.  Notice to Proceed received 12/14/2005. completed (62 A/N).  January 5, 2005 - Design for 62 A/N commenced.  April 2005 - Additional survey, design started.  July 2005 - Budget approved.  Notice to Proceed received 12/14/2005.  2/20/2006 - 60% submittal to FDOT.  5/17/06  95% drawings sent out and SWFWMD permit submitted. 6/06 Re-design project. 10/06 62nd A/N - Design to FDOT. 200 A D March
05054-112 AKCA, Inc. C 324059.94 FDOT LAP - BICYCLE ROUTE IMPROVEMENTS FY 05 - FPN#40648425801 1 S/N and 1S/S from 30 A/N to 62 A/N and more 37 05054-112 05054-112 P 80 3 3/08 Project close out. not been completed April 25, 2005 - Completed First street side path feasibility. May 2005 - Awaiting comments from Transportation Planning regarding feasibility report. July 2005 - Annual striping contractor bid to be renewed August 12, 2005.  2/06 Met with FDOT to dis- cuss projectscope. Evaluating scope revisions. 10/06 Awaiting first set of work orders and plans. 12/06 Continue Design 1/07 Finalize Design L Hollingworth AKCA, Inc. 200 A C March
05066-110 City D 0 SHORE ACRES TIDAL BACKFLOW PREVENTION RETROFIT Shore Acres 01 05066-110 05066-110 P 30 3 04/08 - Begin Design April 2005 - Completed initial prioritization matrix.  May 2005 - Completed Cost Estimate.  7/06 One tide flex valve installed, install one per month. 9/06 Stormwater Installing One Valve per Month. 200 M D March
05090-110 George F. Young, Inc. D 47235 ARTERIAL CHANNEL "E" DREDGING Coquina Key Area 30 05090-110 05090-110 P 1 3 Construction On Hold  04/08 - SWTOD to install Seagrass Buoys 4/07 Complete construction. 10/05 Survey complete. 10/06 Need ACOE Permit. 420 A D March
05104-110 Marine Contracting Group, Inc. C 38900 SAD CANAL DREDGING - HUNTINGTON S/NE & MASSACHUSETTS A/NE Huntington S/NE and Massachusetts A/NE 26 05104-110 05104-110 P 1 3 4/08 Start construction. September 2005 - Issued NTP.  3/21/06 Received preliminary plans for dredging. 10/06 Resolve Easement. Tony Corson Marine Contracting Group, Inc. 200 A C March
06047-110 Marine Contracting Group, Inc. C 573100 ARTERIAL CHANNEL P  DREDGING Riviera Bay and Bayou Grande 30 06047-110 06047-110 P 1 3 Continue Dredging 3/07 Complete construction. 4/06 Permit application; FDEP, ACOE and PCWNA. 10/06 Finalize Permits. Tony Corson Marine Contracting Group, Inc. 200 A C March
06053-111 PBS & J Incorporated D 56545 NE WRF ODOR CONTROL 1160 - 62nd Avenue Northeast 07 06053-111 06053-111 P 97 3 04/08 - Submit for Building Permit  04/08 - Prepare 100% Design  05/08 - Review 100% Design 12/9/05 NTP to TBE Group, Inc. for $ 30,012.  Allowance of $5,812 remaining.   1/06 Data acquisition.  4/06 Draft preliminary engineering report.  7/06  Bioway and Vapex presentation. 10/06 Task Order for final design/workorder approval. 420 A D March
06056-110 TBE GROUP, INC. D 99993 GRAND CANAL BLVD NE BRIDGE REPLACEMENT OVER GRANDE CANAL Grand Canal & Kansas Avenue 04 06056-110 06056-110 P 100 3 08/08 - Prepare Bid Documents  09/08 - Advertise  10/08 - Open Bids Survey will be completed by end of January 2006. Consultant to start design and geotechnical for substructure.  2/06 NTP was issued for consultant. Survey completed. Geotechnical underway. 3/06 Consultant submitted proposed typical section for the bridge  Approved typical was forwarded to TBE. Preliminary design underway.  Received 30% plans for review. Forwarded plans to utilities for review and comment, will submit review comments to TBE first week of May.  Review comments of 30% plans forwarded to consultant to be incorporated into 75% plans.  6/06 Continue final plans/specs. Submit permits to agencies.  A Public Information meeting was held on 7/13/2006. Approximately thirty (30) residents attended the meeting. Plans were described and shown to to the residents. Questions were answered. Residents to submit window shape selection for concrete bridge railing to the City. 10/06 Review 95% Documents. Submit County Permit. 420 A D March
06117-111 City D 0 NE WRF PLATTING 1160 - 62 Avenue Northeast 07 06117-111 06117-111 P 25 3 04/08 - Development Services Reviewing Platt  05/08 - Council Approve Platt 200 M D March
07039-121 Land & Water Engineering Science, Inc. D 23740 NE WRF - LAND RECLAMATION 1160 - 62 Avenue Northeast 07 07039-121 07039-121 P 80 3 8/07 Respond to FDEP comments.  9/07 FDEP review process.  10/07 FDEP and COE permits. 12/06 Permit for Pond De-watering & Vegetation Control burning. 420 A D March
07083-121 City D 0 STORMWATER POND MAINTENANCE & MONITORING AT NE WRF SITE-FDEP 52-0168628-004 1160 - 62 Avenue Northeast 39 07083-121 07083-121 P 5 3 05/08 - Field Inspection  Ongoing - Monitor and Report on Pond as Required 200 M D March
00186-019 City D 0 4TH STREET BUSINESS DISTRICT Multiple Sites 41 00186-019 00186-019 P 4 Hardscape construction anticipated to begin in July with completion anticipated for Spring 2008; landscape work to proceed upon completion of work by General Contractor.  Landscape estimates to be provided to Engineering in early March; permit drawing pr 3/31/08 Preparation of landscape cost estimate and implementation schedule in progress. 200 M March
02049-110 APAC Southeast, Inc. C 2364118.91 FDOT-LAP-DOWNTOWN RESURFACING SR 595 (4 A) FROM 5 A/N TO 3 S/N SR 595 (4th St) from 5th Ave N To 3rd St N 07 02049-110 02049-110 P 95 4 4/08 Install Thermo striping. Prepare Punch List January 20, 2004 - Received and distributed 95% design to FDOT and City.  April 2004 - FDOT review process.  February 4, 2005 - Advertise for bids.  February 25, 2005 - Addendum No. 1.  March 9, 2005 - Bid opening.  April 28, 2005 - City Council award date.  May 2005 - Contract award process.  5/20/05 - Utility schedule forwarded to Ms. Jenkins at FDOT. 10/31/05 FDOT check list and revised specification to FDOT for approval.  11/05 City forwards LAP check list to FDOT. 1/12/06 Supplement agreement No.4 forwarded to FDOT for approval.  4/06 FDOT approval for bidding.  5/06 Federal Highway Administration (FHWA) approval.  5/06 NTP from FDOT for construction phase.  6/06 Advertise for bids.  7/19/06 Prebid meeting.  10/06 Council Approve LAP. Bruce Stenfors APAC Southeast, Inc. 200 A C March
02050-110 APAC Southeast, Inc. C 3797445.7 FDOT-LAP-DOWNTOWN RESURFACING SR 687 (3 ST) FROM 5 A/S TO 5 A/N SR 687 (3rd St) from 5th Ave S To 5th  Ave N 07 02050-110 02050-110 P 90 4 4/08  Complete construction - Except added activities to contract.  5/08 Install decorative crosswalks. 6/08 Install Swinging Mast Arms. January 20, 2004 - Received and distributed 95% design to FDOT and City.  April 2004 - FDOT review process.  February 4, 2005 - Advertise for bids. April 28, 2005 - City Council award date.  May 20, 2005 - Utility schedule forwarded to Ms. Jenkins at FDOT. 10/31/05 FDOT check list and revised specification to FDOT for approval.  1/12/06 Supplement agreement No.4 forwarded to FDOT for approval.  4/06 FDOT approval for bidding.  5/06 Federal Highway Administration (FHWA) approval.  7/19/06 Prebid meet ing.  10/06 Council Approve LAP. Bruce Stenfors APAC Southeast, Inc. 200 A C March
02051-110 APAC Southeast, Inc. C 3330027.6 FDOT-LAP-DOWNTOWN RESURFACING SR 687 (4 ST) FROM 5 A/N TO 5 A/S SR 687 (4th Ave) from 5th Ave N To 5th Ave S 07 02051-110 02051-110 P 90 4 4/08  Complete construction - Except added activities to contract.  5/08 Install decorative crosswalks. 6/08 Install Swinging Mast Arms. January 20, 2004 - Received and distributed 95% design to FDOT and City.  April 2004 - FDOT review process.  February 4, 2005 - Advertise for bids. April 28, 2005 - City Council award date.  May 20, 2005 - Utility schedule forwarded to Ms. Jenkins at FDOT. 10/31/05 FDOT check list and revised specification to FDOT for approval.  1/12/06 Supplement agreement No.4 forwarded to FDOT for approval.  4/06 FDOT approval for bidding.  5/06 Federal Highway Administration (FHWA) approval.  7/19/06 Prebid meet ing.  10/06 Council Approve LAP. Bruce Stenfors APAC Southeast, Inc. 200 A C March
03087-119 Aduddell Industries Restoration C 551500 MUNICIPAL SERVICES CENTER GARAGE - REPAIR Municipal Services Center garage-one-fourth S/N 04 03087-119 03087-119 P 100 4 12/07 - Award Construction Contract  01/08 - Begin Construction September 27, 2004 - Notice to Proceed issued.  September 2004 - Shop drawings were submitted and they are being reviewed for approval.  October 2004 - Carbon Fiber material delivery will delay project.  October 28, 2004 - Work schedule and sequence of operations discussed in meeting. Detail schedule provided. November 29, 2004 - Carbon Fiber rods delivered. Thirty (30) days to install. December 2005 - Carbon fiber reinforcing complete. Sealing of deck underway. February 22, 2005 - Meeting held with contractor.  March 2005 - Complete construction - Final inspection.  March 2005 - Resolve issues; Floors 1-A & B, and 6-A & B.  March 17, 2005 - Deck slab leaks noted.  April 19, 2005 - Meeting held with SSI representative to discuss water leaks, PBQD to propose alternative sealant.  May 11, 2005 - Meeting held with PBQD to discuss design options for deck sealant.  May 17, 2005 - Meeting with Carlisle representative held to discuss sealant topping products. June 2005 - Engineering evaluation of alternatives for deck sealant and finish coat are being tested for adhesion and appearance. July 2005 - Deck topping samples installed. August 2005 - Complete evaluation of alternative products. Tim Hume Aduddell Industries Restoration 200 M C March
05053-112 City D 0 TRAFFIC SAFETY FY2005 - PEDESTRIAN IMPROVEMENTS - COFFEE POT BLVD/21 A/NE/SNELL Coffee Pot Blvd/21 A/NE/Snell 37 05053-112 05053-112 P 95 4 04/08 - Review 100% Design  05/08 - Submit to SWTOD for Construction  06/08 - Begin Construction March 23, 2005 - Design 95% complete - Transporation Planning Department review.  May 2005 - Transportation Planning instructs Engineering to place project ON HOLD pending bike lane installation. 10/06 ON HOLD. 200 M D March
05099-112 City D 0 INTERSECTION MODIFICATION - 22 A/NE & COFFEE POT BLVD NE 22 A/NE and Coffee Pot Blvd/NE 33 05099-112 05099-112 P 100 4 04/08 - Prepare 100% Design  05/08 - Prepare Final Bid Documents  05/08 - Advertise Project August 2005 - Design is 25% completed. September 2005 - 25% design completed - Sent for utility check. 11/05 Design completed. 10/06 Combine with Road Re-construction. 200 M D March
05107-112 Ayres Associates Inc. D 26895 4 S/N (5 A/N to 30 A/N) BEAUTIFICATION - CITY PORTION 4 S/N (5 A/N to 30 A/N) 02 05107-112 05107-112 P 100 4 04/08 - FDOT Verifying Right-of-Way  04/17/08 - Pre-ad Meeing  04/08 - FDOT Review  05/08 - Advertise August thru September 2005 - Title searches for properties.  2/06 Begin property acquisition.  LAP expected to be approved March 2, 2006 by City Council.  2/2/06 LAP approved by City Council and forwarded to FDOT for execution and Notice to Proceed. LAP agreement executed on 3/28/06. Control and specific purpose survey is underway. Property acquisitions continue. 10/06 Finalize Scope and Fee with Ayres. 420 A D March
05334-017 Angle & Schmid Inc. C 204434.3 REBUILD ROBERTS RECREATION CENTER 1246 - 50 A/N 42 05334-017 05334-017 P 4 Complete building demolition.  Commence final site work in April.  Complete site work in May. 03/31/08- Recreation Dept. operations moved into new building. Demolition of old buildings pending utility (Verizon and Progress Energy) clearance to complete site work (60 days after demolition). 200 A March
06042-110 City D 0 SAD ALLEY PAVING - BTWN 6 & 7 S/N FROM 8 TO 9 A/N 6 & 7 S/N FROM 8 TO 9 A/N 26 06042-110 06042-110 P 100 4 04/08 - Finalize Project  05/08 - Initiate Project Close Out 11/05 Survey complete.  1/06 25% plans sent for utility checks. 10/06 Construction. 200 M D March
06071-112 AKCA, Inc. C 4298.36 34 A/N - OAKWOOD GARDENS - PAVEMENT MARKING PLAN 34 A/N between 16 S/N and 21 S/N 37 06071-112 06071-112 P 100 4 Project Close Out in Progress 3/21/06 Received work order.  7/26/06 Forwarded plans for approval from Traffic Planning.  8/21/06 Received comments from TPD.  8/06 Forward revised plans to TPD. 10/06 Review Comments back from TPD. 200 A D March
06075-110 City D 0 SIDEWALK - OAKWOOD GARDENS NEIGHBORHOOD Various locations 23 06075-110 06075-110 P 100 4 Project Close Out in Progress 6/06 Transfer to CDBG funding.  7/06  100% Design.  8/06 Bid. 9/06 Bid. 200 M D March
06077-110 Aduddell Roofing & Sheet Metal C 299967 MIDCORE PARKING GARAGE - MAINTENANCE AND REPAIR 149 - 2 Street North 30 06077-110 06077-110 P 99 4 4/08 Expansion joints replaced under warranty. 10/06 Issue NTP to Contractor. Tim Hume Aduddell Restoration Division 200 A C March
06085-112 Sprinkle Consulting, Inc. D 17550 4 S/N HISTORIC BUSINESS DISTRICT - PEDESTRIAN CROSSWALK AT SUNKEN GARDENS 4 Strett North at Sunken Gardens 33 06085-112 06085-112 P 95 4 Finalize FDOT Review 420 A D March
06088-112 City X 0 1 S/N & 38 A/N - INTERSECTION MODIFICATION 1 Street North & 38 Avenue North 33 06088-112 06088-112 P 0 4 Project Close Out in Progress Determination of required right-of-way.  8/06 Survey.  10/06 Right of Way Acquisition. 200 M D March
06089-112 Sprinkle Consulting, Inc. D 11862 30 A/N & 1 S/N - TRAFFIC CIRCLE DESIGN 1 S/N &  30 A/N 33 06089-112 06089-112 P 100 4 Project Close Out in Progress 8/06 Draft drawings submitted.  10/06 Review Draft. 420 A D March
06114-119 Vinmar Waterproofing & Concrete Restorat C 17875 PIER ELECTRICAL REPAIR 800  Second  A/NE 04 06114-119 06114-119 P 100 4 Project Close Out in Progress 10/06 Process Work Order. Prepare Bid Documents. 200 A D March
06121-112 Purvis Curbs Corp. X 19759 21 A/N WEST OF 2 S/N - RAISED CROSSWALK 21 A/N west of 2 S/N 33 06121-112 06121-112 P 100 4 200 A D March
06379-019 Wannemacher Russell Architects, Inc. D 1996.03 COLISEUM UPGRADE RESTROOM FIXTURES FY06 535 - 4 A/N 42 06379-019 06379-019 P 4 Bid project in April 2008. Construction in July-September 2008. 03/31/08- Pending to issue task order to Architect to re-issue drawings. 420 A March
06380-019 Master Consulting Engineers Inc D 670 COLISEUM EXTERIOR PAINTING & WATERPROOFING FY06 535 - 4 A/N 42 06380-019 06380-019 P 4 Bid project in April 2008. Construction in July-September 2008. 3/31/2008  Pending to issue task order to Architect to re-issue drawings. 420 A March
06402-017 Biltmore Construction C 450000 NORTHSHORE POOL SPLASH PAD 901 Northshore D/NE 43 06402-017 06402-017 P 4 Completed.  Follow up on minor items 3/31/08 HRS to inspect, Biltmore to get C.O.  Close out project. 200 M March
07034-110 City D 0 BAY S/NE ROADWAY RECONSTRUCTION FROM 22 A/NE TO 23 A/NE Bay Street N.E. from 22 A/NE to 23 A/NE 04 07034-110 07034-110 P 95 4 04/08 - Prepare 100% Design  05/08 - Prepare Final Bid Documents  05/08 - Advertise Project 200 M D March
07035-110 City D 0 22 A/NE ROADWAY RECONSTRUCTION FROM COFFE POT BLVD TO 1 S/NE 22 Avenue N.E. form coffee Pot Blvd to First S/N 04 07035-110 07035-110 P 95 4 04/08 - Prepare 100% Design  05/08 - Prepare Final Bid Documents  05/08 - Advertise Project 200 M D March
07056-119 Vinmar Waterproofing & Concrete Restorat C 26400 PIER DOLPHIN PARKING LOT SEAWALL REPAIR 800 - 2 A/NE 04 07056-119 07056-119 P 100 4 Project Close Out in Progress 200 A D March
07084-110 B & A Contractors, Inc. C 319118 PIER PREVENTIVE MAINTENANCE PROGRAM FY 2008 800  Second  A/NE 04 07084-110 07084-110 P 3 4 4/08 Start construction. B. Stenfors B & A Contractors, Inc. 200 M C March
07407-019 Kone Inc. C 10317.3 PIER FACILITY IMPROVEMENTS FY07 800 - 2 A/NE 42 07407-019 07407-019 P 4 Award elevator improvements. 03/31/08- Working on bid package for sole source to Kone. Expected to go to Council for approval in June 2008. Work to be  done in Summer and early Fall of 2008. 200 A March
07413-019 City D 0 SUNKEN GARDENS PARK IMPROVEMENTS FY07 1825 - 4 S/N 41 07413-019 07413-019 P 4 Project to be closed out in May. 3/31/08 Procurement of site furnishings and signage in progress. 200 M March
07417-019 West Coast Glass C 90000 COLISEUM EXTERIOR DOOR REPLACEMENT FY07 535 - 4 A/N 42 07417-019 07417-019 P 4 Transfer funding to another Coliseum project 03/31/08-Determine what funding is left after award of the interior paint project to determine amount of doors that can be repaired and/or replaced. 200 M March
07419-019 Midway Services C 66815 SUNSHINE CENTER HVAC REPLACEMENT 330 - 5 S/N 44 07419-019 07419-019 P 4 It is anticipated that all reports will be presented by April 4th,2008 any and punch list completed in early April. 3/31/2008 Compressor failed on unit in Bldg #2, contractor replaced same. T&B was performed on all units. Manufacturer performed start-up test. 200 A March
08054-119 City D 0 PIER ROOF TOP UNIT HVAC REBUILD 800 Second Avenue Northeast 30 08054-119 08054-119 P 25 4 04/08 - Proceed with AC Procurement  05/01/08 - Council approve Procurement  06/08 - Begin Installation 200 M D March
08210-117 Wannemacher Russell Architects, Inc. D 18141 RESTROOMS IN PARKS FY08 - NORTHSHORE (KIDS AND KUBS) 615 - 2 A/NE 43 08210-117 08210-117 P 4 Advertise, award, begin work. 3/31/08 WRA completed plans. Submit to Building Department.  Reviewed plan with Parks and Recreation Departments. 420 A March
08211-019 City D 0 SUNKEN GARDENS IMPROVEMENTS FY08 1825 - 4 S/N 42 08211-019 08211-019 P 4 define scope of work and bid jobs 3/31/08 No Change 200 M March
08221-017 Nite Owl Irrigation, Inc. D 2676 NORTH SHORE POOL IMPROVEMENTS FY08 901 Northshore D/NE 43 08221-017 08221-017 P 4 Authorize design services.  Commence design on bleacher cover, order bleachers, relocate building. 3/31/08 Ladelfa to revise task order which will include researching codes, design and permit, prepare bid package. 200 A March
08223-017 City D 0 PIER HVAC & PLUMBING 800 - 2 A/NE 42 08223-017 08223-017 P 4 Define scope of work. 03/31/08 HVAC project transferred to Steve Marshal. Define scope of work for plumbing repairs. 200 M March
08224-017 City D 0 PIER ELEVATOR 800 - 2 A/NE 42 08224-017 08224-017 P 4 Award elevator improvements. Expected to go to Council for approval in June 2008. Work to be  done in Summer and early Fall of 2008. 03/31/08- Working on bid package for sole source to Kone. 200 M March
08225-017 City D 0 MIRROR LAKE LIBRARY ROOF/WATERPROOFING 280 - 5 S/N 40 08225-017 08225-017 P 4 Finalize phasing plan and bid documents in April.  Confirm scope to be advertised.  Advertise in May 3/31/08 Meeting held with consultant to determine ability to further phase project and reduce cost. 200 M March
08232-018 City D 0 FIRE STATION #8 REPLACEMENT 40 08232-018 08232-018 P 4 Finalize site selection by Fire Department and City Administration.  Schedule public input sessions with neighborhood and Friends of Boyd Hill. 3/31/08 developed alternate site plans for final evaluation and approval. 200 M March
08234-017 City D 0 CRESCENT LAKE PARK IMPROVEMENTS 1320 - 5 Street North 43 08234-017 08234-017 P 4 200 M March
03034-111 Advanced Engineering & Design, Inc. D 11300.5 PINELLAS BAYWAY FDOT FPID 256903-1-52-02 Pinellas Bayway 18 03034-111 03034-111 P 100 5 04/08 - Close Out Project (New Project 08034-111) January 2004 - Final JPA plans approved by FDOT.  May 2004 - Obtained FDOT Right-of-Way permit number 04-H-799-0034 (DOT UTIL - 11C).  July 2005 - FDOT to delay the project until July 2006. Current published FDOT letting date of 2/20/2007. 420 A D March
03100-110 City D 0 CLAM BAYOU STORMWATER INFRASTRUCTURE IMPROVEMENTS Clam Bayou 18