Engineering & Capital Improvement   
Design  and  Construction  Project  Status  
   
    Project Title  
City   Project Address   
Council Project No. Designer, Consultant or Contractor  
District Project Phase Construction Contract Amount  
  % Complete Project Manager   Activities through March   Three month projection
       
0 05046-111 COSME WTP GROUND STORAGE TANK AND VALVE REPLACEMENT   January 14, 2005 - Kick-off meeting.  April 1, 2005 - Preliminary PDR received.  April 29, 2005 - Preliminary PDR review meeting. September 2, 2005 - Draft PDR review meeting. 10/06 Request Design Proposal from G&H.   04/08 - Prepare 100% Design  05/08 - Submit 100% Design  06/08 - Submit for Permits  07/08 - Finalize Bid Documents  
  Design 16015 Racetrack Road, Odessa, FL 33566    
  95% Greeley and Hansen Engineers    
         
    David Abbaspour    
 
 