Engineering & Capital Improvement   
Design  and  Construction  Project  Status  
   
    Project Title  
City   Project Address   
Council Project No. Designer, Consultant or Contractor  
District Project Phase Construction Contract Amount  
  % Complete Project Manager   Activities through March   Three month projection
       
0 06109-111 BRIDGE - JOE'S CREEK & 62 S/N DRAINAGE IMPROVEMENTS - 8" WM REPLACEMENT   9/06 NTP to Advanced Engineering. Project scope increased from 42 A/N to 46 A/N.  Revised JPA sent to Pinellas County. Advanced Engineering to provide an Engineers Estimate by 10/06. 11/06 Plans and engineer's estimate.   03/08 - Finalize Current Activities  04/08 - Initiate Project Close Out  
  Design Joe's Creek & 62 S/N    
  97% Advanced Engineering & Design, Inc.    
         
    Brendan Lynch    
   
IndexIndexIndexIndexIndexIndexIndexIndex
IndexIndexIndexIndex