Engineering & Capital Improvement   
Design  and  Construction  Project  Status  
   
    Project Title  
City   Project Address   
Council Project No. Designer, Consultant or Contractor  
District Project Phase Construction Contract Amount  
  % Complete Project Manager   Activities through March   Three month projection
       
1 03089-111 NW WRF - DIFFUSED AERATION CONVERSION   January 2004 - North aeration tank drained and cleaned.  January 23, 2004 - Technical memorandum on new blower building submitted by MPI.  February 3, 2004 - Review meeting to discuss blower building.  March 3, 2004 - Mactec submitted report on inspectioNovember 4, 2004 - City Council award for final design Task Order.  May 16, 2005 - 75% design review. July 19, 2005 - Refeived 90% plans and specifications. July 25, 2005 - Plans and specifications forwarded for review. July 28, 2005 - Engineer estimateforwarded.  3/06 Preadvertisement meeting, building permit.  4/06 FDEP permit and Building Permit applications.  9/06 Final plans & specs.  10/06 Advertise.  12/06 Open bids.   4/08 - Continue Construction. 5/08 - Continue Construction. 6/08 - Continue Construction  
  Construction 7500 - 26 A/N    
  70% Wharton-Smith Inc.    
    $4,520,000    
    David Abbaspour    
   
IndexIndexIndexIndexIndexIndexIndexIndex
IndexIndexIndexIndex