|
1 |
03103-111 |
PINELLAS
BAYWAY FORCE MAIN REPLACEMENT-PHASE 2 (DESIGN & BIDDING) |
|
September
24, 2003 - Issued Notice to Proceed to Advanced Engineering. December 11, 2003 - Meeting with FDOT on
site. May 7, 2004 - 75% review meeting
with Water Resources Department.
August 4, 2004 - 90% review meeting with WRD. January 19, 2005 -Review meeting to revise
design. March 2005 - Reviewed scope
and fee, negotiation and work order amendment pending. Due to the change of scope of work this
project will re-start as work order amendment. April 22, 2005 - Project status meeting.Workorder
Amendment forwarded for approval. June 16, 2005 - City Council contract
award. June 29, 2005 - NTP. August 2005 - Survey soft bore. 3/06 Preadvertisement meeting. 4/06 Awaiting clearance from Progress
Energy for final design. 5/06 95% Design.10/06 Obtain FDOT Permit. |
|
04/15/08 - Open Bids 04/08 - Evaluate Bids 05/08 - Award Contract 06/08 - Begin Construction |
|