1 |
06083-112 |
TRAFFIC
CIRCLE - PARK S/S & VILLA GRANDE A/S |
|
4/23/06
Workorder completed. 6/19/06 Kick-off
meeting. Survey in progress. 8/06
Survey completed. 10/06 Review Draft
Preliminary Design. |
|
04/08 - Finalize Evaluation with
Neighborhood Associaton 05/08 - Revise
Design As-needed 06/08 - Finalize Bid
Documents |
|
|
|
Design |
Park S/S
& Villa Grande A/S |
|
|
|
|
|
|
|
|
95% |
Sprinkle
Consulting, Inc. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Ziba
Mohammadi |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|