Activities
through March |
|
Three month projection |
|
|
|
|
|
|
|
|
2 |
00032-311 |
RECLAIMED
WATER SYSTEM - PCCP REPLACEMENT - PHASE II |
|
|
|
Project on Hold |
|
|
|
Design |
1 S/N
from 72 A/N TO 78 A/N & 1 S/N along 77 A/N |
|
|
|
|
|
|
|
|
35% |
City |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
David
Abbaspour |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|