Activities
through March |
|
Three month projection |
|
|
|
|
|
|
|
|
2 |
00064-119 |
GANDY
BLVD WIDENING FROM 28 S/N TO DR MARTIN LUTHER KING JR S/N (9 S/N) |
|
January
16, 2003 - Received SWFWMD permit.
January 17, 2003 - Received FDOT permit. 12/05 Follow-up meeting with FDOT regarding
upcoming project. 1/06 City/FDOT
decision regarding construction phase of this project. 2/27/06 Meeting with FDOT regard-ing land
swap for Gandy/16th Street. 9/06 Negotiate
with FDOT regarding land swap.
10/06 City Council approval of the land swap with FDOT. |
|
04/08 - Finalize Land Swap &
Construction Agreement 04/08 - NTP for
PDE Study 04/17/08 - Council Approve
LAP 05/08 - Add Federal Requirements
to Specifications 06/08 - Council
apporve Land Swap & Construction Agreement |
|
|
|
Design |
Gandy
Blvd from 28 S/N to Dr Martin Luther King |
|
|
|
|
|
|
|
|
95% |
Tampa
Bay Engineering, Inc. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
David
Abbaspour |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|