2 05088-111 LS 69 ANALYSIS   May 23, 2005 - Workorder approved. June 7, 2005 - Notice to Proceed issued to TBE for $30,855.00. June 15, 2005 - Meeting with Pinellas County Public Works Department to discuss the scope of work.  June 24, 2005 - Memo review meeting.   June 2005 -Received project Memorandum. September 16, 2005 - Work order amendment approved final design plans and Technical Memo for ultimate flow projections.  4/06 Final report. 10/06 Finalize Report.  12/06 Final report review meeting.   6/07 Project Close Out in Progress  