| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Engineering
& Capital Improvement |
|
|
|
Design
and Construction Project
Status |
|
|
|
|
|
|
|
|
|
Project Title |
|
|
|
City |
|
Project Address |
|
|
|
Council |
Project No. |
Designer, Consultant or Contractor |
|
|
|
District |
Project Phase |
Construction Contract Amount |
|
|
|
|
% Complete |
Project Manager |
|
Activities
through March |
|
Three month projection |
|
|
|
|
|
|
|
|
2 |
05387-019 |
NORTH
BRANCH ROOF WATERPROOFING |
|
03/31/08
Project still on hold |
|
|
|
|
|
|
861 - 70
A/N |
|
|
|
|
|
|
|
|
% |
City |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Lloyd
Thomas |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|