Engineering
& Capital Improvement |
|
|
|
Design
and Construction Project
Status |
|
|
|
|
|
|
|
|
|
Project Title |
|
|
|
City |
|
Project Address |
|
|
|
Council |
Project No. |
Designer, Consultant or Contractor |
|
|
|
District |
Project Phase |
Construction Contract Amount |
|
|
|
|
% Complete |
Project Manager |
|
Activities
through March |
|
Three month projection |
|
|
|
|
|
|
|
|
2 |
07004-710 |
SIDEWALK
- 4 S/N FROM 110 TO 112 A/N |
|
|
|
Construction by City Forces
Add handrail per FDOT |
|
|
|
Design |
4 S/N
FROM 110 TO 112 A/N |
|
|
|
|
|
|
|
|
90% |
City |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Tony
Leno |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|