3 |
04042-111 |
NE
WRF GRAVITY BELT THICKENER REPLACEMENT |
|
December
4, 2003 - NTP issued to consultant for Basis of Design Report (BODR). January 8, 2004 - BODR kick-off
meeting. March 3, 2004 - Receive draft
BODR. March 23, 2004 - Draft BODR
design review. April 13, 2004 - Tampa
Bay Engineering (TBE) submitted revised site layout. April 29, 2004 - Site layout review
meeting. May 19, 2004 - Receive final
BODR. June 7, 2004 - Work order
amendment circulated for signatures.
July 16, 2004 - Limited NTP for detail design. August 3, 2004 - Design
kick-offmeeting. February 22, 2005 -
90% plans & Specifications. March
17, 2005 - 90% design review meeting held.
April 14, 2005 - 100% plans.
May 23, 2005 - Received 100% plans and specifications. May 23, 2005 - 100% plans and
specifications distributedfor review.
June 6, 2005 - 100% review meeting.
August 3, 2005 - 100% review meeting. August 30, 2005 - Application
for building permit. 2/01/06 Prebid
meeting. 2/16/06 Bid opening. 4/06 Bids to high. Combine with NW Diffused
Aeration and bid inJune 2006. 10/06 Advertise. 12/06 Open bids. |
|
04/08 - Continue Construction 05/08 - Continue Construction 06/08 - Continue Construction |
|