Engineering & Capital Improvement   
Design  and  Construction  Project  Status  
   
    Project Title  
City   Project Address   
Council Project No. Designer, Consultant or Contractor  
District Project Phase Construction Contract Amount  
  % Complete Project Manager   Activities through March   Three month projection
       
3 04042-111 NE WRF GRAVITY BELT THICKENER REPLACEMENT   December 4, 2003 - NTP issued to consultant for Basis of Design Report (BODR).  January 8, 2004 - BODR kick-off meeting.  March 3, 2004 - Receive draft BODR.  March 23, 2004 - Draft BODR design review.  April 13, 2004 - Tampa Bay Engineering (TBE) submitted revised site layout.  April 29, 2004 - Site layout review meeting.  May 19, 2004 - Receive final BODR.  June 7, 2004 - Work order amendment circulated for signatures.  July 16, 2004 - Limited NTP for detail design.  August 3, 2004 - Design kick-offmeeting.  February 22, 2005 - 90% plans & Specifications.  March 17, 2005 - 90% design review meeting held.  April 14, 2005 - 100% plans.  May 23, 2005 - Received 100% plans and specifications.  May 23, 2005 - 100% plans and specifications distributedfor review.  June 6, 2005 - 100% review meeting.  August 3, 2005 - 100% review meeting. August 30, 2005 - Application for building permit.  2/01/06 Prebid meeting.  2/16/06 Bid opening.  4/06 Bids to high. Combine with NW Diffused Aeration and bid inJune 2006. 10/06 Advertise.  12/06 Open bids.   04/08 - Continue Construction  05/08 - Continue Construction  06/08 - Continue Construction  
  Construction 1160 - 62 A/NE    
  30% Wharton-Smith Inc.    
    $2,547,000    
    David Abbaspour    
 
IndexIndexIndexIndexIndexIndexIndexIndex
IndexIndexIndexIndex