Design  and  Construction  Project  Status  
   
    Project Title  
City   Project Address   
Council Project No. Designer, Consultant or Contractor  
District Project Phase Construction Contract Amount  
  % Complete Project Manager   Activities through March   Three month projection
       
3 05054-112 FDOT LAP - BICYCLE ROUTE IMPROVEMENTS FY 05 - FPN#40648425801   April 25, 2005 - Completed First street side path feasibility. May 2005 - Awaiting comments from Transportation Planning regarding feasibility report. July 2005 - Annual striping contractor bid to be renewed August 12, 2005.  2/06 Met with FDOT to dis-cuss projectscope. Evaluating scope revisions. 10/06 Awaiting first set of work orders and plans. 12/06 Continue Design 1/07 Finalize Design   3/08 Project close out.not been completed  
  Construction 1 S/N and 1S/S from 30 A/N to 62 A/N and more    
  80% AKCA, Inc.    
    $324,060    
         
Brejesh Prayman
 