Activities
through March |
|
Three month projection |
|
|
|
|
|
|
|
|
3 |
06056-110 |
GRAND
CANAL BLVD NE BRIDGE REPLACEMENT OVER GRANDE CANAL |
|
Survey
will be completed by end of January 2006. Consultant to start design and
geotechnical for substructure. 2/06
NTP was issued for consultant. Survey completed. Geotechnical underway. 3/06
Consultant submitted proposed typical section for the bridge Approved typical
was forwarded to TBE. Preliminary design underway. Received 30% plans for review. Forwarded
plans to utilities for review and comment, will submit review comments to TBE
first week of May. Review comments of
30% plans forwarded toconsultant to be incorporated into 75% plans. 6/06 Continue final plans/specs. Submit
permits to agencies. A Public
Information meeting was held on 7/13/2006. Approximately thirty (30)
residents attended the meeting. Plans were described and shown toto the
residents. Questions were answered. Residents to submit window shape
selection for concrete bridge railing to the City. 10/06 Review 95%
Documents. Submit County Permit. |
|
08/08 - Prepare Bid Documents 09/08 - Advertise 10/08 - Open Bids |
|
|
|
Design |
Grand
Canal & Kansas Avenue |
|
|
|
|
|
|
|
|
100% |
TBE
GROUP, INC. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|