Engineering & Capital Improvement   
Design  and  Construction  Project  Status  
   
    Project Title  
City   Project Address   
Council Project No. Designer, Consultant or Contractor  
District Project Phase Construction Contract Amount  
  % Complete Project Manager   Activities through March   Three month projection
       
3 06056-110 GRAND CANAL BLVD NE BRIDGE REPLACEMENT OVER GRANDE CANAL   Survey will be completed by end of January 2006. Consultant to start design and geotechnical for substructure.  2/06 NTP was issued for consultant. Survey completed. Geotechnical underway. 3/06 Consultant submitted proposed typical section for the bridge Approved typical was forwarded to TBE. Preliminary design underway.  Received 30% plans for review. Forwarded plans to utilities for review and comment, will submit review comments to TBE first week of May.  Review comments of 30% plans forwarded toconsultant to be incorporated into 75% plans.  6/06 Continue final plans/specs. Submit permits to agencies.  A Public Information meeting was held on 7/13/2006. Approximately thirty (30) residents attended the meeting. Plans were described and shown toto the residents. Questions were answered. Residents to submit window shape selection for concrete bridge railing to the City. 10/06 Review 95% Documents. Submit County Permit.   08/08 - Prepare Bid Documents  09/08 - Advertise  10/08 - Open Bids  
  Design Grand Canal & Kansas Avenue    
  100% TBE GROUP, INC.    
         
   
Fred Dargahi
   
 
IndexIndexIndexIndexIndexIndexIndexIndex
IndexIndexIndexIndex