Engineering & Capital Improvement   
Design  and  Construction  Project  Status  
   
    Project Title  
City   Project Address   
Council Project No. Designer, Consultant or Contractor  
District Project Phase Construction Contract Amount  
  % Complete Project Manager   Activities through March   Three month projection
       
4 02049-110 FDOT-LAP-DOWNTOWN RESURFACING SR 595 (4 A) FROM 5 A/N TO 3 S/N   January 20, 2004 - Received and distributed 95% design to FDOT and City.  April 2004 - FDOT review process.  February 4, 2005 - Advertise for bids.  February 25, 2005 - Addendum No. 1.  March 9, 2005 - Bid opening.  April 28, 2005 - City Council awarddate.  May 2005 - Contract award process.  5/20/05 - Utility schedule forwarded to Ms. Jenkins at FDOT. 10/31/05 FDOT check list and revised specification to FDOT for approval.  11/05 City forwards LAP check list to FDOT. 1/12/06 Supplement agreementNo.4 forwarded to FDOT for approval.  4/06 FDOT approval for bidding.  5/06 Federal Highway Administration (FHWA) approval.  5/06 NTP from FDOT for construction phase.  6/06 Advertise for bids.  7/19/06 Prebid meeting.  10/06 Council Approve LAP.   4/08 Install Thermo striping. Prepare Punch List  
  Construction SR 595 (4th St) from 5th Ave N To 3rd St N    
  95% APAC Southeast, Inc.    
    $2,364,119    
    David Abbaspour    
 