4 |
02049-110 |
FDOT-LAP-DOWNTOWN
RESURFACING SR 595 (4 A) FROM 5 A/N TO 3 S/N |
|
January
20, 2004 - Received and distributed 95% design to FDOT and City. April 2004 - FDOT review process. February 4, 2005 - Advertise for bids. February 25, 2005 - Addendum No. 1. March 9, 2005 - Bid opening. April 28, 2005 - City Council awarddate. May 2005 - Contract award process. 5/20/05 - Utility schedule forwarded to Ms.
Jenkins at FDOT. 10/31/05 FDOT check list and revised specification to FDOT
for approval. 11/05 City forwards LAP
check list to FDOT. 1/12/06 Supplement agreementNo.4 forwarded to FDOT for
approval. 4/06 FDOT approval for
bidding. 5/06 Federal Highway
Administration (FHWA) approval. 5/06
NTP from FDOT for construction phase.
6/06 Advertise for bids.
7/19/06 Prebid meeting. 10/06
Council Approve LAP. |
|
4/08 Install Thermo striping. Prepare
Punch List |
|