4 |
02050-110 |
FDOT-LAP-DOWNTOWN
RESURFACING SR 687 (3 ST) FROM 5 A/S TO 5 A/N |
|
January
20, 2004 - Received and distributed 95% design to FDOT and City. April 2004 - FDOT review process. February 4, 2005 - Advertise for bids.
April 28, 2005 - City Council award date.
May 20, 2005 - Utility schedule forwarded to Ms. Jenkins atFDOT.
10/31/05 FDOT check list and revised specification to FDOT for approval. 1/12/06 Supplement agreement No.4 forwarded
to FDOT for approval. 4/06 FDOT
approval for bidding. 5/06 Federal
Highway Administration (FHWA) approval.
7/19/06 Prebid meeting. 10/06
Council Approve LAP. |
|
4/08
Complete construction - Except added activities to contract. 5/08 Install decorative crosswalks. 6/08
Install Swinging Mast Arms. |
|