4 02051-110 FDOT-LAP-DOWNTOWN RESURFACING SR 687 (4 ST) FROM 5 A/N TO 5 A/S   January 20, 2004 - Received and distributed 95% design to FDOT and City.  April 2004 - FDOT review process.  February 4, 2005 - Advertise for bids. April 28, 2005 - City Council award date.  May 20, 2005 - Utility schedule forwarded to Ms. Jenkins atFDOT. 10/31/05 FDOT check list and revised specification to FDOT for approval.  1/12/06 Supplement agreement No.4 forwarded to FDOT for approval.  4/06 FDOT approval for bidding.  5/06 Federal Highway Administration (FHWA) approval.  7/19/06 Prebid meeting.  10/06 Council Approve LAP.   4/08  Complete construction - Except added activities to contract.  5/08 Install decorative crosswalks. 6/08 Install Swinging Mast Arms.  
  Construction SR 687 (4th Ave) from 5th Ave N To 5th Ave S    
  90% APAC Southeast, Inc.    
    $3,330,028    
    David Abbaspour    
 