Activities
through March |
|
Three month projection |
|
|
|
|
|
|
|
|
4 |
05053-112 |
TRAFFIC
SAFETY FY2005 - PEDESTRIAN IMPROVEMENTS - COFFEE POT BLVD/21 A/NE/SNELL |
|
March
23, 2005 - Design 95% complete - Transporation Planning Department
review. May 2005 - Transportation
Planning instructs Engineering to place project ON HOLD pending bike lane
installation. 10/06 ON HOLD. |
|
04/08 - Review 100% Design 05/08 - Submit to SWTOD for
Construction 06/08 - Begin
Construction |
|
|
|
Design |
Coffee
Pot Blvd/21 A/NE/Snell |
|
|
|
|
|
|
|
|
95% |
City |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Brejesh
Prayman |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|