Engineering & Capital Improvement   
Design  and  Construction  Project  Status  
   
    Project Title  
City   Project Address   
Council Project No. Designer, Consultant or Contractor  
District Project Phase Construction Contract Amount  
  % Complete Project Manager   Activities through March   Three month projection
       
4 05334-017 REBUILD ROBERTS RECREATION CENTER   03/31/08- Recreation Dept. operations moved into new building. Demolition of old buildings pending utility (Verizon and Progress Energy) clearance to complete site work (60 days after demolition).   Complete building demolition.  Commence final site work in April.  Complete site work in May.  
    1246 - 50 A/N    
  % Angle & Schmid Inc.    
    $204,434    
         
Jean Totti