Activities
through March |
|
Three month projection |
|
|
|
|
|
|
|
|
4 |
06380-019 |
COLISEUM
EXTERIOR PAINTING & WATERPROOFING FY06 |
|
3/31/2008 Pending to issue task order to Architect to
re-issue drawings. |
|
Bid project in April 2008. Construction in
July-September 2008. |
|
|
|
|
535 - 4
A/N |
|
|
|
|
|
|
|
|
% |
Master
Consulting Engineers Inc |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Jean
Totti |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|