Project Facts

The West Central Avenue Streetscape Project has three basic components: streetscape design, watermain replacement, and branding. The project limits are from Park Street east to 58th Street. The update to the West Central Master Plan will be informed by public input as it establishes a vision and a brand for the area. The design will work with the City’s Complete Streets Implementation Plan regarding desired operating speeds and multimodal networks.

Online Public Survey   Project Info Sheet 

About West Central Avenue

The Central Avenue corridor in St. Petersburg is a major east-west connector, where north and south St. Petersburg meet, linking residents and visitors to downtown, to beaches, and all the businesses in between.

Construction Timeline

The project is slated for construction to begin in late 2019 and for completion in late 2020.

Central Avenue Revitalization Plan

In 2012 the City created the Central Avenue Revitalization Plan in response to the desire to create a “unified vision for Central Avenue that allows the individual districts to develop and maintain their unique identities.” Since 2012 the Central Arts, Edge, and Grand Central Districts have undergone street improvements, contributing to the economic vibrancy of those areas.

Key Project Information

  • Design will be data-driven in conjunction with public input and this project’s fiscal constraints. 
  • Improvements include: curb ramps, sidewalk, bike lanes, enhanced crossings, mast arm traffic signal poles, and landscaped medians. 
  • Some disruptions to access can be expected during construction; therefore, schedules of construction will be communicated. 
  • Watermain construction may interrupt typical service for about an hour at a pre-scheduled time. 
  • Funding is provided by Penny for Pinellas and City of St. Petersburg Water Resources Department. 

What’s in store for West Central Avenue?

  1. Reconstructing curb and curb ramps, sidewalks, and driveways for safety and ADA Compliance. 
  2. Replacing span wires with new mast arm traffic signal poles at three intersections. 
  3. Enhancing crosswalks at four intersections. 
  4. Potentially installing new landscape medians and pedestrian crossings along the corridor. 
  5. Addressing street lighting. 
  6. Creating a brand for the West Central District for future implementation. 

While the West Central Streetscape Project is under construction, the City will also be replacing the water main with an 8-inch waterline along the northern edge of the roadway and place most meters underground.

Stay Informed

 
 

Public Workshops

The same information will be presented at the three workshops.
Saturday, October 27, 2018 
freeFall Theatre
6099 Central Ave.
10:30 am

Monday, October 29, 2018
St. Petersburg College - Gibbs
6605 5th Ave. N Science Building, SC 232
5:30 pm

Thursday, November 8, 2018
Brentwood at St. Pete Assisted Living
6280 Central Ave.
10:30 am

Public Input Opportunities

Public Surveys
Public Survey #1 – (Open: October 20 – November 9)
Answer survey online using SurveyMonkey

Public Survey #2 – (Open: December 4 – December 14)
Link to come

Public Meetings
Public Meeting #1: Tuesday, December 4, 2018 (Concepts Input)
freeFall Theatre
6099 Central Ave.
6:30 pm 

Public Meeting #2: Tuesday, January 22, 2019 (Concept for Design)
freeFall Theatre
6099 Central Ave.
6:30 pm

Print page Text resize: Increase font size Decrease font size Original font size Updated:

City of St. Petersburg
P.O. Box 2842
St. Petersburg, FL 33731

  • p: 727-893-7111
  • f: 727-892-5102
  • tty: 727-892-5259
Copyright City of St. Petersburg St. Pete TV - Off The Air