Northeast Water Reclamation Facility Improvements Project

Print this page

Northeast Water Reclamation Facility Improvements Project 

Project Overview

The Northeast Wastewater Reclamation Facility (NEWRF), located at 1160 62nd Ave. NE., provides essential wastewater and reclaimed water services for the Northeast Service Area. The NEWRF was originally constructed in the 1950s and has undergone various expansions and upgrade projects throughout the years with the last major upgrade completed in 1981. The NEWRF has a permitted capacity of 16 million gallons per day annual average daily flow.

The improvements at the NEWRF will not only improve safety, maintenance and operations, but also enhance reliability, resiliency and sustainability for the facility and the community. The key components of the project include:

  • Upgrading the facility’s electrical distribution system with modern equipment due to its age, deteriorated condition and diminishing availability of replacement parts.
  • Renovating the distribution pump system to increase efficiency and reliability of pumping reclaimed water to our customers.
  • Installing a deep injection well to provide additional capacity for treated reclaimed water disposal during wet weather flows (providing operational flexibility and infrastructure redundancy).
  • Widening the sidewalk along 62nd Avenue for safer and easier pedestrian/cyclist usage.

The project is currently in the design phase and will comply with the City Code requirements for Envision (City Code Chapter 2 Article 5 Division 5, Sustainability and Resiliency of City Facilities). Envision is an independent infrastructure rating system for evaluating and rating the community, environmental and economic benefits of infrastructure projects.

POTENTIAL PUBLIC IMPACTS

Construction will be limited to within the NEWRF site. Once construction begins, neighboring residents, schools and businesses may hear construction activity on weekdays, from 7 a.m. to 7 p.m. At times, work at night or on the weekend may be required as these are generally times of lower plant flows and this will minimize service interruptions. During these instances, residents will receive advance notice of any work that occurs outside of normal construction hours.

Residents may also notice construction traffic in the area. Construction traffic, including heavy equipment deliveries, will access the NEWRF from the facility entrances on 62nd Ave. NE.

Project Timeline

  • Through Fall 2022: Complete Design and Permitting
  • Spring 2023: Contractor to Mobilize to Site and Construction Start
  • Spring 2026: Construction Complete

Schedule is subject to change based on weather, permitting or other unforeseen conditions.

Project Updates

October 5, 2022: Public Meeting Oct. 19

Public Input Opportunities

Public Meetings

Public Meeting #1
Wednesday, Oct. 13, 2021 at 6 p.m.

Public Meeting #2
Wednesday, Oct. 19, 2022 at 6:30-7:30 p.m. 
Shore Acres Recreation Center Multi-Purpose Room
4230 Shore Acres Blvd. NE.

Public Input Survey

The public is invited to complete the below survey about the project.

Community Outreach Survey 

Documents